A price per square metre is one line of the budget. A method for the rest, the benchmarks we could verify and a worked example with hypothetical numbers.
Most self-build budgets fail for a simple reason: they are built from one number, the price per square metre of construction, and that is one line out of eight. Land, design, permits, utility connections, landscaping, furnishing, taxes and a reserve all sit outside it. This guide gives a method for the whole budget, the cost benchmarks we could verify and an honest list of what we could not, a typical timeline and a worked example with hypothetical numbers. Nothing here is a quote or a promise: costs depend on the country, the region, the design and the builder, and they change.
A budget method in eight lines
1. Land, including the survey and any clearing. 2. Purchase taxes and fees on the land. 3. Design and permits: architect, engineer, surveys, permit fees, supervision. 4. Construction: floor area multiplied by a price per square metre that is written into an itemised quote. 5. Utilities and access: electricity, water, drainage or septic system, road, internet. 6. Landscaping, boundary walls and a pool if you want one. Pools are usually priced separately. 7. Furnishing and fit-out items that are not in the builder's scope. 8. A contingency. As a rule of thumb, which is not a statistic, plan for 15 to 25 percent of everything except the land, and keep it untouched until it is needed.
Ask every bidder to mark each item as included, excluded, provisional, owner-supplied or not applicable. One Bali guide makes exactly this point, and it is the single most useful habit for comparing quotes.
What published benchmarks say, and what they do not
Benchmarks help you sanity-check a quote. They do not replace one.
- International city averages. Turner & Townsend's 2025 construction market survey reports building costs in US dollars per square metre, as averages across all building types, for work underway at the start of 2025 and excluding taxes. Reported figures include about 5,744 for New York, about 5,386 for Zurich and Geneva, about 5,385 for London and about 1,150 to 1,170 for Hanoi and Ho Chi Minh City. These are not residential prices for a single house, and they are city-level averages, so use them only to see how wide the spread is. A regional UAE report from the same firm gives an average of AED 5,500 per square metre for residential high-rise apartments in Dubai and Abu Dhabi in 2025.
- Cost inflation. Eurostat's producer price index for new residential buildings rose by about 48 percent between 2015 and 2025 across the EU, according to reports on its 2026 key figures, with much larger rises in Bulgaria (about 166 percent), Hungary (about 155 percent) and Romania (about 131 percent). This is an index of contractors' prices, not what you will pay, but it shows why an old per-square-metre figure is a poor guide.
- Thailand. Guides we found give widely different ranges in baht per square metre: 15,000 to 25,000 for a basic house in one, 25,000 as a minimum for a standard house and 40,000 for a luxury one in another, 25,000 to 45,000 in a Phuket guide, and 25,000 to 60,000 or more in a July 2026 article that also notes a rise in ready-mix concrete prices. Several exclude land, design, permits and supervision.
- Bali. One 2026 guide gives US dollars 850 to 1,100 per square metre for a standard villa, 1,200 to 1,600 for mid-range luxury and 1,800 to 2,500 or more for high-end; another gives 700 to 1,100 for luxury. One source adds roughly 300 to 600 dollars per square metre for finishes and landscaping with reliable contractors, and says pools are priced separately.
Most of the Thai and Bali figures come from builders, agents and property sites that sell building or villas, and the ranges disagree. Treat them as a way to spot a quote that is far outside the range, in either direction. We did not find reliable current benchmarks for the Mediterranean countries.
How long it takes
There is no honest single number, because timelines are dominated by permits and by the builder's capacity.
- Permits. Guides give very different ranges: for Greece 45 to 90 days in one and three to nine months in another; for Thailand two to six months or more. The municipality knows its own queue; ask it.
- Construction. One Bali source speaks of an eight to twelve month construction cycle for a villa, and notes that the shortage of skilled mechanical and electrical engineers often stretches it.
- Around the build. Land purchase and checks, design, utility connections, finishing and snagging add months on both sides of the construction itself.
What usually causes overruns
- Scope that is not written down, so every change is priced as an extra.
- Provisional sums for items that were never specified, such as tiles, kitchens or windows.
- Price rises between the quote and the purchase of materials; the Eurostat index above shows the direction.
- Currency: if you pay in a currency other than the one you earn in, the exchange rate is a budget line.
- Site conditions found after work starts: rock, groundwater, a failed soil test.
- Permit delays that leave you paying rent and finance costs.
- Owner-supplied items that arrive late or are the wrong size.
- Disputes that stop work. See architects, builders and contracts abroad.
A worked example with hypothetical numbers
These numbers are invented to show the method. They are not a market price, a quote or a forecast. Take a 150 square metre house.
- Land: 120,000 euros plus 8 percent purchase taxes and fees, which is 9,600, so 129,600.
- Construction: 150 square metres at a hypothetical 1,800 euros, which is 270,000.
- Design and permits: 22,000.
- Utilities and access: 18,000.
- Landscaping and pool: 35,000.
- Furnishing: 25,000.
Everything except the land comes to 370,000. A 20 percent contingency on that is 74,000. The base budget without the contingency is 499,600 and with it 573,600.
Now test it.
- Scenario A: construction prices rise 15 percent between quote and purchase (40,500 more) and the permit slips six months, so you pay 1,200 a month in rent for six months (7,200). The extra is 47,700, which is inside the contingency and leaves 26,300.
- Scenario B: construction is 25 percent over (67,500), the utility connection costs double (18,000 more) and the delay is nine months of rent (10,800). The extra is 96,300, so the total is 595,900, which is 22,300 above the budget with contingency.
The lesson is not the totals. It is that a 20 percent reserve survives a moderate bad year and not a bad one, and that the construction line is under three quarters of the non-land cost.
Using the method
- Get at least three itemised quotes with the same scope.
- Put the permit and the utility connection costs in writing from the municipality or the utility, not from the builder.
- Keep the contingency in a separate account and spend it only on documented changes.
- Decide in advance what you will cut if the budget is under pressure.
The sequence of steps is in buying land to build a home abroad; for a ready-built alternative see off-plan purchase abroad: contracts, escrow and delays and developer instalment plans. For Bali, Thailand and the Mediterranean see ownership, permits and pitfalls for foreigners.