The delay clauses that decide your position, how the rules differ in a few countries, what the data on stalled projects shows and what to do step by step.
Every off-plan contract promises a completion date, and the date is the part buyers read least. When a project runs late, what you can do depends on a handful of clauses and on the law where the building stands. This guide sets out the clauses to look for, how the rules differ in a few countries, what the data on stalled projects shows and the steps to take. For the general mechanics of an off-plan purchase see our guide on contracts, escrow and delays by country (off-plan purchase abroad); this one goes deeper on the delay itself. It is general information, not legal or financial advice. A completion date is a target, not a promise, and money paid into an unfinished project can be lost.
What "delay" means in the contract
Read the definition before you read the remedies. The contract usually names a target date, and then adds time before a delay counts:
- A grace period, often counted in months, during which a late handover is not treated as a breach. The length is in the contract; some run to a year, so read the number.
- Events that extend the date automatically, usually grouped as force majeure or "events beyond the developer's control".
- A long-stop date, the outer date after which you may terminate. Without one, a project can be late indefinitely without giving you a right to leave.
Be wary of a force majeure clause that lists supply problems, labour shortages, permits or a contractor's failure. Those are ordinary risks of building, and a developer who can invoke them freely can extend the date without limit. Ask for the clause to list only genuinely external events.
The clauses that decide your position
- Liquidated damages: a fixed compensation for each month of delay after the grace period. Look for the rate, the cap, whether it is paid in cash or credited against the price, and whether it starts from the target date or from the end of the grace period.
- Right to terminate and refund: after the long-stop date, or after a stated delay, can you cancel, and do you get everything back, with interest, and how fast?
- What you paid is protected by what: a registered escrow account, a bank guarantee, an insurance policy, or nothing but the developer's promise. A right to a refund is worth what stands behind it.
- Notice rules: how and where you must give written notice, and in which language. A notice sent the wrong way may not count.
- Your own payment duty: whether you must keep paying while the project is late, and whether you may withhold a milestone payment that has not been earned.
How the rules differ by country
These are summaries from secondary sources (law-firm blogs, consumer-organisation and news pages). We did not read the statutes in full, so check the current text with a local lawyer before relying on any point.
- Spain. Money advanced for a home under construction must be covered by a guarantee. The regime was a 1968 law until 1 January 2016 and is now set in an additional provision of the building-regulation law of 1999, so which one applies depends on the contract date. Sources describe the guarantee as covering the amounts advanced plus legal interest, and the Supreme Court has confirmed in 2024 that the guarantor answers to buyers. The standard contract clause, however, says a delay is not a breach and gives no compensation, and a short delay on its own is generally not enough to cancel.
- Turkey. Prepaid housing sales fall under the Consumer Protection Law (Articles 40 to 46) and the Code of Obligations governs default. Sources say the developer must refund what was paid with interest from the payment dates, and that for larger projects the buyer's money has to be backed by a completion insurance or a bank guarantee. One source adds that noting the contract in the land registry protects the unit. Sources disagree on the withdrawal periods, and a 2026 change in the law was reported but not checked, so take the current text from a Turkish lawyer.
- United Arab Emirates (Dubai). Each off-plan project must have a registered escrow account, and when the regulator formally cancels a project the refunds come from that account. A delay on its own does not automatically let you terminate: it depends on the sale and purchase agreement, the cause of the delay and the project's official status. The sources disagree on how much of your money returns at different stages of completion, so we give no figures. See our Dubai guides (purchase checklist and investment risks).
- Thailand. We did not verify the rules for delay and refund. Our guide to developer checks and payments there is the place to start (off-plan in Thailand).
For the markets where we publish country guides, see Montenegro, Georgia, Zanzibar and the Dominican Republic.
What the data says on delays: two very different pictures
Published numbers pull in opposite directions, and neither is a forecast for your project.
In Greater Santo Domingo a survey by the national statistics office, reported by elDinero, found 59.8% of 6,682 registered construction projects halted at the time of the survey, against 60.6% in the second half of 2025, with 4.3% abandoned. Stalling was more common in small projects. The survey covers all registered projects, including small ones, not only off-plan sales to foreigners, so it shows how common stopped sites are in that area, not the chance that a particular off-plan project fails. We summarise it here (the Santo Domingo survey).
In Dubai the Land Department figures reported by Gulf News show 24,537 homes delivered in the first half of 2026, up more than 36% on a year earlier, with some developers handing over early. Off-plan made up 74% of residential sales by volume in the same period, according to REIDIN. We summarise it here (Dubai handovers). One strong period is not a guarantee about the next, and the figures say nothing about any single developer.
What the two pictures have in common: the record of the developer and the money protection in the contract matter more than the market average. See how to check a developer (how to verify a developer abroad).
What to do, step by step
1. Read your contract and note the target date, grace period, long-stop date and notice rules. Write down the dates. 2. Collect evidence: dated photos of the site, progress reports, the developer's messages and any announced new dates. Keep everything in writing. 3. Ask the developer in writing for the current schedule and the reason for the delay. Send it the way the contract requires. 4. Do not stop paying without advice. Stopping payments can put you in default and weaken your position. Whether you may withhold a payment that is tied to a milestone not yet reached is a question for your lawyer. 5. Take an independent lawyer, not the one the seller recommends (why a seller-recommended lawyer is a conflict of interest). 6. If a refund is due, claim it from what stands behind your money: the escrow, the guarantee or the insurer, and check the deadlines. Some guarantees have time limits or conditions for a claim. 7. If the project is at risk of stopping, check the permits too (missing permits).
When the project stops altogether
If the developer becomes insolvent, buyers are usually creditors in a queue, and whether you are ahead of the bank depends on how your payments were secured. See what protects a deposit (deposit protection when a developer goes bankrupt). An escrow account or a guarantee that you can call directly puts you in a very different position from an unsecured payment to the developer.